2838894c65
The Blocker 1 commit lands in the base fork (commit 676af02e on
redbear-working). This commit:
1. Bumps the three submodule pointers to the new commits that
the gitea force-pushes landed this session (one per fork).
2. Updates QUIRKS-SYSTEM.md to reflect the new state.
In QUIRKS-SYSTEM.md:
- Recent Activity (2026-06) table: adds a row for Blocker 1
with the commit SHA + summary.
- Blocker status block: Blocker 1 promoted to RESOLVED, Blocker
4 re-tagged as reduced to a 1-2 day follow-up (the loop is
mechanically unblocked now that Blocker 1 is in), Blocker 3
flagged as the next priority.
- Test count progression: extends to 140 (12 new pcid unit
tests).
- Blocker 1 section: new 'Status: RESOLVED 2026-06-07' block
with the three pieces (PcidConfigWriter, build_device_info,
apply_pci_quirks), the wiring location, the test coverage,
and the clean check / clippy result.
- Cross-Cutting Consumer Wiring Checklist: pcid row promoted
from PENDING to RESOLVED, with the commit SHA + test count.
The '3 of 5' line below becomes '4 of 5'.
- Adjusted Phase Estimates: R17 and R19 drop from 5-7 days to
2-3 days (the Blocker 1 dependency is gone). New total is
42-62 days (was 47-72); the +2-day remainder is Blocker 3
plus the xhcid QuirkAction follow-up.
- Recommended Implementation Order: Blocker 1 step promoted
from PENDING to RESOLVED, with the new commit SHA and
test count inline.
No other sections changed. The 15 medium/low gaps from the
R1-R10 audit remain PENDING; the next session will land
Blocker 3 (usbhidd HID/USB wiring) as the only remaining P0
critical blocker.
base
@ 676af02e08
bootloader
@ c7cdcb5d25
installer
@ 101a836a92
kernel
@ a4ba465a86
relibc
@ d7115781bf