Merges findings from both boot audits into a single authoritative plan: - 0. Current state (12 patches, 3 targets, completed phases) - 1. Priority matrix (P0 blocking → P4 deferred) - 2. P0 — 2 blocking issues (boot redbear-full, clean build verify) - 3. P1 — 4 critical gaps (D-Bus runtime, ion job control, tab completion, DRM in boot) - 4. P2 — 4 high priority (shadow support, rate limiting, network in initfs, polkit) - 5. P3 — 6 medium priority (ion features, fbcond, ACPI sleep, thermal, battery) - 6. P4 — 6 deferred items - 7. Week-by-week implementation order with parallel opportunities - 8. Acceptance gates (G1-G5) - 9. Total effort: ~103h / ~13 days solo, ~1 week with 2 devs